Wood Dale Public Works Committee receives resurfacing project update
The Wood Dale Public Works Committee met Aug. 11 to receive an update on the Mill Road Resurfacing project.
Here is the meeting's agenda, as provided by the committee:
1
PUBLIC WORKS COMMITTEE
August 11, 2016
PUBLIC WORKS
COMMITTEE MINUTES
Committee Date: August 11, 2016
Present: Ald. Catalano, Jakab, Messina, Sorrentino, Susmarski, E.
Wesley, R. Wesley & Woods
Absent: None
Also Present:
Meeting Convened at:
Treasurer Porch, Chief Greg Vesta, K. Chrisse, K. Rubach
8:38 p.m.
APPROVAL OF THE MINUTES:
The minutes of the July 14, 2016 meeting were approved as presented.
REPORT & RECOMMENDATION:
Approval of Contract with Martam Construction for the Edgebrook Lift Station
Improvements in an Amount Not to Exceed $489,070.00
DISCUSSION:
None
VOTE:
Ald. Woods made a motion, seconded by Ald. R. Wesley, to approve a contract with
Contract with Martam Construction for the Edgebrook Lift Station Improvements in a
not-to-exceed amount of $489,070.00.
A roll call vote was taken, with the following results:
Ayes: Ald. Catalano, Jakab, Messina, Sorrentino, Susmarski, E. Wesley, R.
Wesley & Woods
Nays: None
Abstained: None
Motion: Carried
ITEMS TO BE CONSIDERED AT FUTURE MEETINGS:
a. Ward 2 Phase IV Design Contract Award (September 8th)
b. Patching Program (September 8th)
c. RA Mancini- Mill Road Water Main Final Payment (TBD)
d. Potter Street Contract Award (TBD)
2
PUBLIC WORKS COMMITTEE
August 11, 2016
ITEMS NOT ON THE AGENDA
? Mayor Pulice asked about grinding corners with the patching program. Assistant
Public Works Director, Ken Rubach, did not recommend that stating that it would
be unsightly and only a short term fix.
? Ald. E. Wesley asked for an update on Murray Drive.
? Ald. Susmarski asked for a status of the Veteran’s Memorial. Ald. Woods stated
that an update will be provided after Streetscape discusses it next month.
? Ald. Catalano asked for a status on Mill Road Resurfacing. Mr. Rubach stated
that they are having the same issue as Murray Drive, although it is a different
contractor.
ADJOURNMENT:
The meeting adjourned at 8:53 p.m.